| Name of the Project |
Addition of Block in Wire Rod Mill |
| Current Capacity |
0.275 MTPA through Garret Route |
| Current Product Range |
11mm to 32mm |
| Upgraded Capacity |
0.3 MTPA through Block Route |
| Upgraded Product Range |
5mm to 18mm High quality wire rod |
| Cost of Project |
INR 71.75 Crore |
| Project Start |
April 2011 |
| Project Commissioning |
July 2012 |
|
|